Report of completed construction works on 31.03.2014
On 28 March, a festive event was organised in order to celebrate the Ridgepole Celebrations of Villa Hepburn.
That was a way for the owners to express their gratitude to the builders, honouring the end of the main building stage – the building frame erection.
Villa Churchill The work on the building separation walls has been completed. The preparatory work for the installation of the ventilation, water supply, sewerage, heating and air conditioning systems has been finished. Villa Dietrich The work on the building separation walls has been completed and the boiler house has been installed. The work of fixing wiring, ventilation, heating and sewerage systems is in progress. The work of installing heating devices has been initiated and the installation of the window blocks and façade systems is in progress.
Villa Hеmingway The building frame erection work has been finished. Soon the builders will be able to take up the wall construction installation.
Villa Tiffany The builders have started the most important work stage: deepening and enforcing the building foundation. The work on the renovation of the building doors, windows, internal coverings and walls is in progress.