Villa Dietrich – constructors have commenced an important construction stage – roofing.
Works on the internal finish of premises have been started: plastering of stairway enclosure and floor arrangement.
Assembly of the building sash pulleys has been finished. Works on window aperture heat insulation are being performed; works on arrangement of heating appliances, development of heating, water supply and ventilation system network in apartments.
Villa Churchill – here works on planking of communication mines are executed. Assembly of uprises of ventilation, water and sewerage, heating and conditioning systems has been finished.
Villa Hepburn – works on assembly of façade systems and filling of window openings have been commenced; roofing works have been started. Assembly of ventilation, water, sewerage and conditioning systems has been finished.
Villa Tiffany – works on reinforcement of the building foundations, replacement of internal partitions and walls of the building are in progress.
Villa Hemingway - roofing works have been started and the window openings have been filled; the structure planking of the building is in progress.