Report of completed construction works on 31.05.2014
Villa Dietrich The interior wall plastering, floor laying and window aperture filling works have been completed in the building;
The internal lift assembly has been finished and the roof light opening glazing has been completed; The building roof-work is continuing, the building separation plaster board walls assembling, façade heat insulation and heating appliances installation works are in progress. The staircase finishing work has been initiated.
Villa Tiffany All the building interior separation walls have been replaced and the ground floor flooring bearing beams have been replaced; The building renovation work is continuing. The builders have started the roofing.
Villa Hеmingway. The building structure panelling is in progress, engineering communications installation work has been initiated, the roofing is continuing.
Villa Churchill Mechanical well panelling is in progress. Window and lift assembly has been started in the building.
Villa Hepburn The window aperture filling works have been completed in the building; the lift has been installed. The façade system installation and building façade heat insulation works are continuing. Heating networks are being installed and wiring fixing work is being done in each floor.