Report of completed construction works on 31.06.2014
Villa Dietrich Works on window blocks and façade systems installation are being completed. The same refers to roofing works.
Works on façade decorative glazing and balcony railings elements installation are in progress.
Internal and external utilities networks are being installed, gypsum board partitions are being mounted, stairwells rails finishing is being done.
Interior works, namely marble laying in the halls and stair rails installation have been started.
Villa Tiffany Building renovation works are being continued. Roofing works and works on the existing foundation strengthening are in progress.
Villa Hemingway Façade and roofing works are completed. Engineering networks are laid out, works on house connection to the city utilities networks are on the way.
Villa Churchill Works on utility system shafts covering and windows installation are being continued. Roofing works have been started.
Villa Hepburn Works on façade systems, balcony railings and windows installation are being continued. Roofing works and façade insulation works are in progress. Heating system network installation and floor wiring works are being done. Lifting equipment installation has been completed.